Services / Equipment:
Detailed Feasibility Studies, Plant Design & Engineering, Feasibility Studies, Due Diligence, Supply Chain Management, Carbon Management, CSR Education Plan
We evaluated the potential for CEVA Logistics’ parent company to explore transforming distribution warehouses into fully off-grid facilities. Our model shows that a 75,000 m² rooftop could produce enough energy for 20 refuelings of the Toyota-powered VDL trucks used in European parts logistics, while also powering the warehouse itself.
Modeled fleet dispatch: 20 Toyota-powered VDL trucks × 39 kg per full fill = 780 kg of hydrogen.
The design called for rooftop solar hydrogen production around the clock. During daylight, the panels supply the depot and the electrolyzers, which use electricity to split water and produce hydrogen. A heat sink and battery backup support the 24-hour electrolysis design. The stored hydrogen can supply stationary fuel cells for warehouse power and trucks returning to the yard.
The opportunity lies in what a depot already brings together. A large roof can generate power, the building can consume it, and a freight schedule identifies when hydrogen customers will arrive.
The wider opportunity is to connect the roof, the warehouse and the fleet as one energy system. Our partnerships with Earendel Solar Energy AB and ARGO-Anleg GmbH bring complementary capabilities to that development approach: solar electricity for hydrogen production, followed by storage, transport and dispensing to place fuel where vehicles need it.
Keep the lights on and the trucks on schedule.
Consider a truck returning just before sunrise. The warehouse still needs power for lighting, handling equipment, and dispatch. The truck needs enough hydrogen for its next route. If stored hydrogen has supplied the building overnight, the station must still have fuel available when that vehicle pulls in.
That overlap makes the hardest question hourly. An annual estimate of rooftop solar generation cannot tell a fleet manager whether the last truck in the morning queue will leave on time. The feasibility work called for hourly site data, minimum and peak building loads, seasonal variation, and route demand. Together, those inputs determine the solar array size, the battery capacity needed to sustain electrolysis, and the hydrogen reserve the building and fleet can draw on.
Use daylight generation across a 24-hour operating cycle
At the reference scale, 75,000 m² of roof is 7.5 hectares. The usable area and local sunlight determine how much electricity the roof can deliver. Keeping electrolysis running after sunset also depends on how much daytime electricity the system can store and how much the warehouse needs overnight.
| Energy path | Job at the depot |
|---|---|
| Rooftop solar to electrical loads | Power the building, supply battery vehicle chargers, and run the electrolyzers during daylight. |
| Daytime generation to battery backup | Store electricity for use outside solar hours: battery capacity and the heat-sink arrangement support 24-hour electrolysis. |
| Hydrogen storage to stationary fuel cells | Convert a portion of stored hydrogen back to electricity when the warehouse needs it, while the remaining inventory covers planned vehicle refueling. |
| Hydrogen storage to truck dispensers | Deliver fuel in the yard at the flow rate the fleet’s departure schedule requires. Water treatment, electrolysis, compression, and storage must support that rate over the operating day. |
Compare three ways to supply the electrolyzers.
Our study scope compared solar-only, grid-only, and combined solar-and-grid electrolysis. The solar-only case tests the independence objective through periods of low generation. The grid-only case gives the operator a comparison for hydrogen cost and carbon intensity using local electricity. The combined case tests how much grid backup would be needed to meet dispatch requirements when solar production is low.
This comparison gives a warehouse operator a specific investment choice. It can assess the cost of the solar capacity and storage required for independence against the cost and emissions of retaining a grid connection. The site model can also compare on-site hydrogen production with buying hydrogen from an outside supplier.
Connecting solar generation to fuel in the truck
Our November 2023 collaboration with Earendel Solar Energy AB explicitly connects logistics warehouse rooftops with electrolyzers and Class 8 fuel cell trucks. For the depot studied here, that connection starts with matching renewable electricity generation to the building’s demand and the electrolyzer’s operating schedule.
Our June 2025 collaboration with ARGO-Anleg GmbH addresses the next part of the chain: hydrogen storage, transport and dispensing. These capabilities connect hydrogen production to the station’s practical duty: having sufficient usable fuel available when the trucks return.
Each company’s role connects to a specific operating requirement. CEVA’s warehouse and freight activities establish the demand context. Earendel’s solar collaboration addresses renewable supply. ARGO’s hydrogen capabilities address fuel handling and delivery. Toyota-powered VDL trucks provide the separately reported vehicle benchmark. Our feasibility and integration work brings those requirements into a common site model.
The value comes from coordinating the whole operating cycle. A large solar array must match electrolysis capacity; hydrogen storage must bridge production and refueling schedules; and dispensers must meet vehicle pressure, flow, and turnaround requirements. This is how the rooftop opportunity becomes a practical fleet-energy proposition.

A refueling opportunity at the scale of a distribution fleet
The 40-tonne VDL truck with Toyota fuel cell modules provides a fleet-specific benchmark. Reporting from the European deployment puts its onboard hydrogen capacity at 39 kg. Using that figure as the nominal empty-to-full fill, 780 kg supplies 20 complete truck fills.
In the illustrative solar day, an 11.025 MWp array delivers 49.72 MWh after PV losses, assuming 70% roof coverage, 210 W/m² of panels, 5.5 peak-sun hours and an 82% performance ratio. The model allocates 12 hours to daytime operation and 12 hours to overnight operation. With a 125 kW average building load, 90% electrical battery round-trip efficiency, and 3 kWh/kg for compression and dispensing, the day requires approximately 48.7 MWh. The remaining 1.0 MWh is insufficient for a 21st full tank on that schedule.
A depot starting dispatch with 1,170 kg of usable hydrogen could dispense 780 kg and retain 390 kg, equivalent to ten full truck fills. The reserve requires an initial charge. Routine fuel-cell power, hydrogen losses, or lower solar yield reduce the fuel available for dispatch. The 20-fill figure is a modeled day and requires an hourly site and station design check.
The DFS gave CMA CGM a basis for evaluating those decisions across its estate. For each candidate depot, the master plan links local solar yield and roof availability to building demand, fleet schedules, water and utility requirements, permitting, and installed cost. A large roof above a quiet yard may have surplus electricity and few fuel customers. A busy depot with limited roof space may have the opposite problem. The most promising sites bring solar supply and recurring freight demand together. Other carriers could become customers where yard access and spare dispensing capacity allow.
The roof opportunity and the fleet demand are both visible in CEVA’s operations.
In 2023, CEVA outlined a roughly $180 million rooftop solar program with its real estate partners. Its 2025 sustainability report recorded nearly 760,000 m² of photovoltaic panels across its worldwide facilities. This is a useful precedent for securing roof access and working with landlords across a portfolio. Our per-depot hydrogen estimate comes from our own feasibility work.
On the fleet side, CEVA announced a five-year hydrogen-truck trial with Toyota Motor Europe in 2023. In 2025, Toyota reported deploying additional heavy-duty fuel cell trucks, with CEVA among the participating logistics providers and a reported range of up to 400 km per refueling for the 40-tonne trucks.
For a warehouse operator, that route detail matters. A depot station can serve trucks where they already stop to exchange freight. Its value depends on whether the operator can deliver the right fuel to the right yard, in the right quantity, before the next departure. That was the commercial question behind our rooftop hydrogen study.
A depot can also become part of a wider circular logistics network. The ARGO announcement identifies a proposed Melbourne tyre-recovery development at pre-FEED evaluation, including hydrogen pathways from solar electrolysis and syngas and intended industrial and logistics vehicle applications. This provides related development context for evaluating fuel supply at the facilities that freight connects. For this warehouse study, the central question remains the same: can the site provide dependable building power and the fuel its returning fleet requires?
1. The depot already has potential customers for both products.
The warehouse consumes electricity, and the fleet consumes fuel. A predictable freight schedule gives the developer a basis for sizing both supplies.
2. Round-the-clock production and peak refueling are different duties.
The heat sink and battery backup support the 24-hour electrolysis design. Hydrogen storage lets the station serve concentrated truck arrivals while preserving a reserve for warehouse power.
3. One master plan can guide many different installations.
Applying the same feasibility method across the portfolio lets CMA CGM compare suitable roofs, fuel demand, and delivered energy costs before choosing which depots to advance.
These takeaways highlight selected lessons from this case study, not an exhaustive account. Klean brings deeper technical expertise and commercial insight to each project through tailored engagements.
Start with a roof plan, an hourly electricity-use profile, and the fleet’s return-to-depot schedule. Add vehicle fuel demand and the time each truck has available to refuel. With those inputs, we can scope an assessment of the generation, storage, and dispensing capacity your operation would require.
We can then connect that operating requirement with the solar, electrolysis, and hydrogen infrastructure needed to turn your warehouse into a dependable energy base for your fleet.
For a new equipment project, a paid Detailed Equipment Quotation (DEQ) establishes the preliminary configuration and investment basis. A Detailed Feasibility Study (DFS) examines site performance and economics before Front-End Engineering Design (FEED).
Discuss Your Warehouse Power and Hydrogen Fleet Project with Klean >> GO.
LEARN MORE
ABOUT THE INFORMATION PRESENTED
We present the case study and the refueling potential at the assessed scale, based on the Australian project, which served as the proof of concept for the global master plan. CEVA’s rooftop solar data and Toyota’s European fleet deployment are distinct public operational references. We address detailed site engineering and operational assumptions through a project-specific engagement.
The Earendel and ARGO-Anleg announcements describe complementary development partnerships. Supplier appointments and equipment selection for an individual depot are established through its engineering and commercial agreements. The 20-fill scenario remains an illustrative modeled day. Solar-electrolysis and syngas-derived hydrogen require separate production and lifecycle emissions assessments.
We support our client’s through our quoting and project development by providing a wealth of information and specifications about Klean Industries systems and technologies.