Mining Waste to Energy Ash for Metals and Mineral Value

Sustainable Development Goals

Project Status:
Technical Commercial Assessment | Independent Technology Review
Organizations Involved:
Klean Industries, Klean Capital, Confidential Technology Developers
Services / Equipment:
Due Diligence, Feasibility Studies, Design & Engineering

We Put a Price on the Gold Going to Landfill. Gold. Silver. Copper. In the ash left after energy recovery. At Klean Industries, our confidential ash-recovery assessment began with a material carrying a disposal obligation. We widened the investment question: what happens when the recovery plant is sized for the whole waste-to-energy system?

The answer changes the opportunity's scale. Applied to the combined planning basis for Palm Beach County’s two renewable energy facilities, our recovery scenario points to about US$32.1 million in annual metal-product proceeds, plus US$25.3 to 31.6 million to process the ash. A conceptual four-module development indicates approximately US$35.9 to 42.2 million annually after operating costs and a capital-replacement reserve, supporting approximately 4.3 to 5.0 years of simple pre-tax payback at steady operation.

These are conditional development economics. The approximately 5,000-tonne trial established core recovery and product sales; the system-wide figures apply the wider proposed recovery profile to public SWA capacity and ash-generation data. They are not measured SWA metal yields or a contracted project.

The Challenge

Recover the value left after energy generation. A waste-to-energy facility sells electricity and recovers metals. Yet the material leaving the ash system still needs a destination. Across SWA’s two facilities, the published planning assumptions imply approximately 358,000 metric tonnes of ash annually at the stated operating basis. That is a recurring industrial feedstock large enough to consider a dedicated recovery business.

SWA already recovers metals and has authorized uses for some ash within its landfill. We therefore focus on the value remaining after existing recovery and on the true cost of the next disposal or beneficial-use route. Additional revenue must come from additional recovery. A published disposal tariff is a negotiation benchmark, not proof of SWA’s internal cost.

The original trial supplied a decisive commercial lesson: its metal products sold, but the operation received no processing fee and stopped to negotiate one. We retain that lesson in the investment structure. Recover the metals and get paid for the ash-management service.

The Solution

Connect operating evidence with the whole ash stream. The approximately 5,000-tonne trial demonstrated continuous core processing, sales of recovered metal products and an aggregate-use contract following leach testing. Our assessment connected that operating evidence with the proposed fine-recovery and combined-ash treatment routes: washing, size separation, gravity concentration and flotation.

We then matched the recovery concept to the whole ash stream. The published planning basis for SWA’s two renewable energy facilities implies approximately 358,000 tonnes of ash annually. Four 100,000-tonne-per-year modules provide 400,000 tonnes of recovery capacity to serve that combined stream.

Each module would be commissioned against secured ash deliveries, with development phased around the temporary reduction during REF 1 replacement and later expansion. The whole-system economics describe steady operation with both facilities supplying ash.

The Outcome

The precious metals matter. At the combined planning volume, the proposed output profile contains approximately 167 kilograms of gold, 916 kilograms of silver and 1,335 tonnes of copper each year. Gold alone represents approximately US$20.9 million in contained benchmark value. After assumed buyer deductions, the modeled gold proceeds are approximately US$13.6 million.

Recovered metal or product Whole-system annual quantity Estimated annual proceeds
Gold 167.5 kg US$13,590,678
Silver 915.9 kg US$930,837
Copper 1,334.8 t US$11,806,533
Aluminum 1,436.2 t US$2,714,435
Zinc 707.7 t US$1,721,792
Lead 353.8 t US$426,078
Coarse ferrous product 6,036 t US$905,436
Total product proceeds   US$32,095,789

The projected proceeds allow for buyer deductions and refining costs. Gold, silver and base-metal quantities come from the wider development model; they are not measured by trial recoveries or assays of SWA ash. Mineral and chemical products receive no sales credit. The supporting economics set out prices, settlement assumptions, and detailed calculations.

The processing fee has an ash-specific local benchmark. SWA’s published incinerator-ash disposal rate is approximately US$88.18 per tonne, compared with US$46.30 for garbage. The ash-management service has value alongside the metals recovered.

Our discounted-fee case charges US$70.55 per tonne, giving the ash supplier a 20% discount to the published ash tariff. The upside case uses the full US$88.18 rate. Both scenarios use the same metal yields and project costs; the processing fee differs. Fees would need to be agreed commercially.

Whole-system annual illustration Discounted ash fee Full-tariff upside
Ash processed 358,474 metric tonnes 358,474 metric tonnes
Metal-product proceeds US$32,095,789 US$32,095,789
Ash-processing fee per metric tonne US$70.55 US$88.18
Annual processing income US$25,289,600 US$31,612,000
Combined revenue US$57,385,389 US$63,707,789
Operating costs at US$50/t US$17,923,703 US$17,923,703
Annual capital-replacement reserve US$3,600,495 US$3,600,495
Annual pre-tax cash contribution US$35,861,191 US$42,183,591
Conceptual project budget US$180,024,751 US$180,024,751
Simple steady-state payback 5.0 years 4.3 years

The US$180 million conceptual budget allows about US$144 million for four process modules, plus US$36 million for site integration, development, and initial working capital. Annual costs include an assumed US$17.9 million operating budget and US$3.6 million capital-replacement reserve. Payback excludes financing, tax, and construction or ramp-up time; site-specific quotations and cash-flow modeling are required before investment.

A 100,000-tonne annual module provides the building block. Four modules give the combined SWA ash stream a dedicated recovery route, with spare capacity and room to phase the investment. That is the progression from the trial: prove the core recovery, develop the industrial module, then match the system to the available ash.

For an integrated owner, the benefit is recovered-product income plus verified avoided ash-management costs, less the recovery plant’s costs. For a separate processor, it is product income plus a contracted treatment fee. Those are two ownership structures for the same opportunity. The fee is not added a second time as an owner saving.

Our next development targets are specific: verify the metals remaining after existing recovery, secure buyers for the products, qualify the mineral outlets and negotiate the ash-service agreement. Those decisions turn the modeled opportunity into an investable project.

3 PROJECT TAKEAWAYS

1. Size recovery for the ash system.

An industrial ash supply can support dedicated recovery capacity. Phase modules around committed deliveries and upstream facility changes.

2. Sell the recovery service as well as the metals.

Use ash-specific disposal alternatives to negotiate a treatment fee. Gold, silver, and copper provide a second income stream when residual grades and buyer terms support it.

3. Prove the margin after existing recovery.

Validate remaining metal content, mineral destinations, and full project costs. Build the investment case around additional value and a defined payback threshold.

These takeaways highlight selected lessons from this case study, not an exhaustive account. Klean brings deeper technical expertise and commercial insight to each project through tailored engagements.

WHAT DO THESE LESSONS MEAN FOR YOUR PROJECT?

Your waste-to-energy plant may already earn from power and metal sales. The ash leaving that plant deserves its own investment assessment. Klean can connect the remaining resource to a recovery configuration, product buyers, and a processing agreement sized to your whole system.

New equipment projects advance through a paid Detailed Equipment Quotation (DEQ), Detailed Feasibility Study (DFS), and Front-End Engineering Design (FEED), with agreed decision gates. Existing-facility and acquisition assessments begin through a separately scoped paid engagement. Bring us the ash stream and the disposal economics; we will define the work needed to establish the investment case.

Develop Your Whole-System Ash Recovery Investment >> GO.

LEARN MORE

ABOUT THE INFORMATION PRESENTED

This case summarizes Klean’s confidential technology-acquisition assessment and a whole-system development scenario using public SWA data. It is not an SWA engagement, approved project, or supply agreement. Recovery performance, product outlets, and commercial terms require project-specific validation. Proprietary information remains confidential; access requires the appropriate permissions and agreed engagement.

Source note: SWA’s published throughput, ash-generation assumptions and disposal tariffs have been converted to metric tonnes. All tonnes on this page are metric. Detailed sources and calculations accompany the economic assessment.

This project addresses the United Nations Sustainable Development Goals 9 (Industry, Innovation and Infrastructure), 11 (Sustainable Cities and Communities), 12 (Responsible Consumption and Production) and 13 (Climate Action), through its focus on metal recovery and qualified mineral outlets. Benefits depend on verified performance and approved destinations.